A release every second Tuesday: what we changed after five forced updates in nine days

Darrell Henry · November 25, 2026 · 5 min read

For six weeks this fall we shipped our clinical documentation app, EMRFlow, about every two days. Every fix was real and most were small. Then we counted what it cost the people using it, and changed how we ship.

The cost we weren't counting

We cut twenty versions between early September and mid-October. Ten of them reached both app stores, and each of those raised the minimum version the app will run. We keep that minimum on purpose: in a clinical record, everyone should be saving under the same rules. But a raised minimum means every therapist's phone has to update before it can open a note.

That's ten raises in six weeks, and five of them landed in nine days. For a therapist, that is an update screen between sessions, sometimes in a family's driveway on a weak signal, for a change they may never notice. We were measuring how fast we fixed things. We weren't measuring how often we interrupted people.

The rule we adopted

On October 22 we moved to a fixed release train:

Four reasons to ship early, written down in advance

A fixed calendar only works if "this can't wait" has a definition before anyone is under pressure. Ours has four (the security reason was added in November), and nothing else qualifies:

  1. A defect that corrupts or misstates a clinical record.
  2. A defect that blocks signing in or saving.
  3. A crash that reaches more than one person.
  4. A confirmed security defect that lets someone act as another person, take a role they weren't given, or see or change data they have no right to, when the fix needs a new app build.

A missing hardening setting or a library advisory with no confirmed way to exploit it here rides the next scheduled train. That last line mattered more than we expected. Without it, almost anything can be argued into a hotfix at 9 PM.

Write the hotfix test before you need it. The decision "is this urgent?" made in the moment, by the person who just found the bug, almost always comes out yes.

The check that decides whether a train leaves

A slower train only helps if what's on it works. In September a defect in how one screen saved reached users while every one of our 489 unit tests passed, because those tests checked small pieces of code and not the app a therapist actually uses. So every release now goes through a smoke test before it reaches anyone: we install the real build from the store's internal test track on a real phone, drive it through the everyday steps (open the list, open a form, approve it, reopen it, edit it, preview its PDF), and check the server's copy after each step, not just the screen. If the server doesn't show the save, the step fails. The store upload tool won't send a build to production without a passing result for that exact build.

Twice since October 22 that test has stopped a build, once in October and once in November. The November one is typical. The first cut of the November train failed on an attendance-log step: a saved log with no patients on it stayed empty on the server, so it never left the internal track. We fixed it, cut the next build the same day, and it passed and shipped on schedule.

Five weeks in

Since October 22, four versions have reached people instead of the ten in the six weeks before. Two were hotfixes, each for one of the written reasons, and two were scheduled trains. Two more builds were stopped by the smoke test before anyone saw them. Ship days are now predictable enough that we put them on the calendar, and so can the practices that use the app.

If you run a small team shipping a mobile app

Release trains aren't our invention, and two weeks is a common choice for them. The written exception covers the fixes that can't wait.